A building construction work can be completed by two masons A and B together in 22.5 days. Mason A alone can complete the construction work in 24 days less than mason B alone. Then mason A alone will complete the construction work in :
Select the correct option:
A
24 days
B
`42 days
C
30 days
D
36 days